Construction

Text "8thStreet” to 1-844-238-0330 to receive 8th Street construction information via text message.

Department:
City Engineering
Public Information - George Hayward
Spring 2025
  • Corridor study and design complete 
Summer-Fall 2025
  • Widen 8th Street bridge over Fountain Creek
Fall–Winter 2025
  • Replace water main, Vermijo Avenue to Motor City Drive
Spring-Summer 2026
  • 8th Street roadway work (concrete/paving)

8th Street Construction

Bridge work continues, girders next month

Crews continue to work on widening the 8th Street bridge over Fountain Creek. This week, concrete work continues on the bridge. Next week, crews will start placing large rocks (“riprap”) in the creek and continue working on the road near the bridge.

  • There will be no construction on Thursday or Friday for the Thanksgiving holiday. Work will start again on Monday, December 1.
  • Right now, the right northbound lane and the right turn lane remain closed. These lanes must stay closed, even when no one is working, because the area behind the barriers is not safe for drivers.
  • More traffic changes are expected in mid-December, when crews will install large bridge beams and start work on the concrete median.
  • This project adds an additional northbound lane across the bridge and replaces the Midland Trail bridge with an attached multi-use path on the bridge. This part of the project will continue through early 2026. During this phase, the bridge will remain open in both directions, although occasional lane closures should be expected.
  • Access to local businesses remains open and clearly visible.

The project team wishes everyone a safe and happy Thanksgiving.