Construction

Text DUBLIN to 866-762-3640 to receive text alerts regarding construction updates and traffic impacts.

Department:
Public Works
Public Works Department
Fall 2024 - Spring 2025

Complete final design and prepare construction documents

Early 2025

Start private utility relocations

Spring 2025 - Fall 2026

Construct storm sewer and surface improvements

Traffic Impacts

  • The full closure of Dublin Boulevard from just east of Fieler Drive to Mustang Rim Drive, originally scheduled to start on May 27, has been delayed. The Dublin Boulevard / Peterson Road intersection will be open next week. Drivers should expect Dublin Boulevard daily lane closures May 27-30. More information will follow.
  • The Sand Creek Trail will be closed in the area near and underneath Dublin Boulevard from May 19 to early August. A trail detour will be signed. Trail users will be directed to use sidewalks and signalized intersections to cross Dublin Boulevard.
  • Travelers should expect equipment and workers adjacent to the road.
  • The posted work zone speed limit may be reduced to 35 mph.
  • Follow signs and flagger directions when present.
  • View the Construction Updates tab for more information on construction and traffic impacts.