Construction Activity Notice

The Colorado Springs Airport is currently constructing a new deice apron on the west side of Taxiway Echo, just north of the Arrival/Departure Airfield Control Group (A/DACG) Facility. The deice pad will also be used during the summer months as United States Forest Service (USFS) tanker base. A new taxi lane will be constructed to connect Taxiway E and the new deice apron. Within this project there are many additional items including utility infrastructure to service the new facility.

Construction Activity and Schedule

 

07/01/2020 – Beginning at 7:00AM the right lane of Milton E Proby Parkway north bound will be closed and speed reduced. The temporary flow fill patch within this closure (East side) will be removed and replaced with asphalt material. This right lane closure will remain in place overnight on Wednesday 07/01/2020. Anticipated opening back to public traffic the morning of 07/02/2020.

07/02/2020 -  Beginning at 8:00AM the left lane of Milton E Proby Parkway north bound will be closed and speed reduced. The temporary flow fill patch within this closure (West side) will be removed and replaced with asphalt material. This left lane closure will remain in place overnight on Thursday 07/02/2020. Anticipated opening back to public traffic the morning of 07/03/2020.

07/03/2020 -  Beginning at 8:00AM both left and right lanes of Milton E Proby Parkway north bound will be open to traffic without any speed reductions in place.